EV charging hub costs have gotten complicated with all the variables and configurations flying around. As an electrician who’s quoted and installed commercial charging infrastructure throughout the Pacific Northwest, I learned everything there is to know about what these projects actually cost. Today, I’ll share it all with you.
What Drives the Cost
Probably should have led with this section, honestly — there’s no single answer because so many factors vary. A small hub with four Level 2 chargers costs dramatically less than a twenty-charger station with DC fast charging. Location, capacity, technology choice, and existing electrical infrastructure all affect the final number.
The Major Cost Components
Equipment Costs
Chargers themselves range from $2,000-$8,000 for commercial Level 2 units to $30,000-$180,000+ for DC fast chargers. The spread is enormous because power levels and features vary widely. Smart charging capabilities, payment processing, and networking add cost but often pay back through better utilization management.
Electrical Infrastructure
That’s what makes electrical work the wild card for charging hub costs — existing infrastructure varies so much. Some sites have adequate power capacity nearby. Others need transformer upgrades, new service entrances, or significant underground conduit runs. This component can range from $10,000 to well over $100,000 depending on site conditions.
Installation Labor
Skilled electrical labor for commercial installations runs $75-$150/hour in the Northwest market. Complex installations requiring trenching, concrete work, and coordination with utilities take more time. Simple installations on prepared sites go faster.
Site Work and Permits
Concrete pads, striping, signage, ADA compliance, and permit fees all add up. Environmental review may be required in some jurisdictions. These “soft costs” can reach 15-25% of hardware costs.
Available Incentives
Federal, state, and utility incentives can offset 30-70% of installation costs. Washington and Oregon both offer significant programs. These incentives change frequently, so check current availability before budgeting.
A realistic budget for a small commercial charging hub (4-8 Level 2 chargers) typically runs $50,000-$150,000 before incentives. Larger installations with fast chargers can exceed $500,000 easily.